Varthur-Gunjur Road Widening Pushed to 2027

Land acquisition delays stall SH-35 elevated corridor, testing East Bengaluru commuters' patience.

Discover More

Varthur-Gunjur Road Widening Delayed Again: Full Relief Only by 2027

The much-awaited widening of the Varthur-Gunjur corridor along State Highway-35 has hit another roadblock, with authorities now confirming that the project will not be ready before 2027. The Karnataka Road Development Corporation Limited (KRDCL) has officially stated that the widening and elevated corridor project along State Highway-35 will not be completed before 2027, extending a wait that has already stretched across several years for residents of Varthur, Gunjur, and neighbouring pockets of East Bengaluru.

The core issue holding up the project is land. Of the 198 properties identified for acquisition, several have been cleared and compensated, but acquisition for 19 properties continues to remain stuck, and this small but stubborn set of parcels has become the single biggest bottleneck to full-scale construction. What began as a fairly contained upgrade has also grown in scope: the slow-moving project, originally intended as a 1.9-km widening initiative, has expanded into a larger redevelopment plan involving a short flyover near Varthur Kodi, and future provisions for a double-decker structure and metro alignment. The revised plan includes expanding the existing 30-metre road to 100 metres, constructing a 1.92-km, 60-ft elevated stretch from Varthur Lake Kodi to Vinayaka Theatre, raising a double-deck structure and accommodating railway alignment requirements.

On the ground, however, progress tells a different story. So far, only drainage work and demolition in limited pockets are visible, while full-scale progress remains stalled. This gap between the ambitious blueprint and the visible pace of work has been a recurring source of frustration for residents who use this stretch daily to reach the Outer Ring Road and other parts of the city.

The corridor's troubles aren't limited to the elevated stretch alone. Nearby, work on the Varthur bridge tells a similar story of stop-start execution: one side of the bridge is ready, work on the second bridge — heading towards the Varthur police station — has been abandoned for the past three years, and the resulting bottleneck near Muthasandra has become notorious among daily commuters. The tender for this bridge, estimated to cost about Rs 20 crore, was revived only after Chief Secretary Shalini Rajneesh inspected the Varthur-Gunjur Road in April 2025 and issued instructions to complete all pending projects. Even so, KRDCL is yet to complete the acquisition of properties, even though engineers have started minor civic works along the stretch — underlining just how tightly the larger corridor's fate is tied to resolving these last remaining land parcels.

Community voices have been vocal about the compounding effect of these delays. Clement Jayakumar, a member of the Mahadevapura Task Force, has pointed out that the government must provide a comprehensive approach to the issues faced by people in the Varthur, Gunjur, and Sarjapur areas, noting that even a small bridge project has been pending for two and a half years while the broader East Airport Corridor has also fallen behind schedule. For many residents, the ask has become far more modest than a full elevated corridor: they say that a motorable road, even without widening or elevated lanes, would bring immediate relief.

In the interim, some relief is on the way in the form of basic road maintenance. The Karnataka State Highway Improvement Project (K-SHIP) division is preparing to take up pothole-filling work across 70 km, including stretches that fall under SH-35, with tenders worth Rs 2.6 crore expected to be floated soon for the task. While this won't fix the underlying congestion, it should at least make the existing carriageway more usable while the larger widening and elevated corridor work continues at its slow pace.

For homebuyers evaluating this stretch of East Bengaluru, the delay is a reminder to factor in realistic connectivity timelines rather than announced ones. The Varthur-Gunjur-Whitefield-Sarjapur Road belt remains one of Bengaluru's most sought-after residential corridors thanks to its IT-park proximity, but unless land acquisition issues are resolved quickly, the corridor may remain under construction for at least two more years, delaying the much-awaited traffic relief. Buyers exploring new homes here should ask developers and brokers for the latest ground status on this project before finalising a decision, particularly if daily commute time to ORR or Whitefield is a priority.

BRIGADE Projects

BRIGADE Secunderabad
Acquisition

BRIGADE Secunderabad

Secunderabad, Hyderabad, Telangana

3, 4 BHK (expected) • Price on request

₹650 Cr GDV project on 2.25 acres

BRIGADE BAIN CAPITAL WHITEFIELD ITPL MIXED-USE DEVELOPMENT
Upcoming

BRIGADE BAIN CAPITAL WHITEFIELD ITPL MIXED-USE DEVELOPMENT

Whitefield, Bangalore

Grade A Office | 5-Star Hotel • Investment ₹2,200 Cr

2 million sq ft mixed-use JV with Bain Capital

BRIGADE BOGADI ROAD
Upcoming

BRIGADE BOGADI ROAD

Bogadi Road, Mysuru

2, 3 BHK • Price on Request

10.9-acre Brigade address near Outer Ring Road

Brigade ECR Resort
Upcoming

Brigade ECR Resort

East Coast Road (ECR), Chennai

Guest Rooms, Suites • Price on request

250-room beachfront resort by Brigade

BRIGADE GRAND HYATT CHENNAI ECR
Upcoming

BRIGADE GRAND HYATT CHENNAI ECR

East Coast Road (ECR), Chennai

200 Keys • Price on Request

Beachfront Grand Hyatt hospitality landmark

BRIGADE INDUSTRIAL PARK
Upcoming

BRIGADE INDUSTRIAL PARK

Devanahalli, Bangalore

Built-to-Suit | IT/ITES | Data Centre • Price on Request

25-acre industrial park, ~2 million sq ft

BRIGADE JW MARRIOTT CHENNAI OMR
Upcoming

BRIGADE JW MARRIOTT CHENNAI OMR

Perungudi, Chennai

250 Guest Rooms & Suites • On Request

9-acre OMR mixed-use hospitality development

Brigade Neopolis Four-Acre Project
Upcoming

Brigade Neopolis Four-Acre Project

Kokapet, Hyderabad

3, 4 BHK • Price on request

4-acre upcoming project in Neopolis

Reach Out

We'd Love to Hear From You

Back

Questions You Might Have

Why has the Varthur-Gunjur road widening project been delayed to 2027?
The delay is mainly due to unresolved land acquisition. Of 198 properties identified for the project, 19 remain stuck in the acquisition process, holding up full-scale construction of the elevated corridor.
What exactly does the Varthur-Gunjur SH-35 project involve?
The plan covers widening the existing 30-metre road to 100 metres and building a 1.92-km, 60-ft elevated stretch from Varthur Lake Kodi to Vinayaka Theatre, along with future provisions for a double-deck structure and metro/railway alignment.
Is there any visible construction progress on the ground?
Progress so far has been limited to drainage work and demolition in a few pockets. Full-scale construction has not started in most stretches due to the pending land acquisition.
Which authority is responsible for this project?
The Karnataka Road Development Corporation Limited (KRDCL) is executing the widening and elevated corridor project, while the K-SHIP division is separately handling interim pothole-repair work on SH-35.
Is there any temporary relief planned for commuters before 2027?
Yes, K-SHIP is preparing a pothole-repair drive covering 70 km, including SH-35, with tenders worth Rs 2.6 crore expected to be floated soon to improve the existing road surface.
What about the Varthur bridge near Muthasandra?
One side of the Varthur bridge is complete, but work on the second span has been stalled for nearly three years. Tenders were revived after a government inspection in April 2025, though the bridge is still awaiting final approval.
How does this delay affect property buyers in Varthur and Gunjur?
Buyers should treat 2027 as an early estimate rather than a firm deadline, given the corridor's history of missed timelines, and evaluate current commute conditions rather than only the promised future connectivity.
Does this delay affect Brigade's projects in the Varthur-Gunjur belt?
Brigade's developments in this corridor, including its upcoming Gunjur township, are positioned along Whitefield-Sarjapur Road and existing internal roads, so day-to-day access is largely independent of the SH-35 elevated stretch, though overall area connectivity will improve once the project completes.
Who is raising these concerns on behalf of residents?
Community representatives such as members of the Mahadevapura Task Force have flagged the compounding impact of multiple stalled projects, including the bridge and the East Airport Corridor, on daily life in the Varthur-Gunjur-Sarjapur belt.
What is the realistic timeline now for full traffic relief on this corridor?
Officials indicate the project may take at least two more years beyond the current estimate if land acquisition issues aren't resolved quickly, meaning residents should plan for continued congestion through 2027 and possibly beyond.

We share this information warmly and in good faith, as a guide only and not as an offer. Details including pricing, plans, and images may change over time. Please confirm everything with us before taking any step. About · Projects